Loghouses - Construction technology.
Building of a wooden house using manually pre-cut timber
blocks is split up into 3 stages:
| Stage 1.
Making of the timber block |
 |
| Stage 2.
Beginning 4 to 8 months after Stage 2 (the time span needed for setting
of the structure), this stage primarily focuses on roof geometry before
finishing works begin; and, when appropriate, roof timbers are corrected.
Once all effects of the log structure shrinkage are eliminated, fit-out
can start |
 |
| Stage 3.
The stage begins through 4 - 8 months after the termination ending
2 stages. The break is necessary for drying a logs of srub. Before
painting and decorating the geometry of a roof is checked and, necessarily,
recovers rafter system. After elimination of consequences drying a
srub it is possible to break to painting and decorating. |
 |
You will find out more about the construction techniques
in a book by Ivan Alekseev «Things you need to know about log houses
construction»
You are welcome to e-mail your questions to us Due to a large workload you
may have to wait for the response for 1 to 10 days.
rusdom-export@yandex.ru
Ivan Alexeev )
Vadim Godyna
Artur )
Jan )
|
|